Planning an embedded generation connection involves coordinating generation equipment with the distribution network’s protection, operating and quality-of-supply requirements. SA Power Networks’ TS131, issued in September 2018, sets out technical requirements for inverter energy systems (IES) above 200 kW and rotating generating systems of any size that operate in parallel with its distribution network. Battery energy storage systems connected through inverters are included as generating units.
The standard is intended to support safe, reliable connections as generation flows increasingly in both directions across a distribution network. Its requirements cover system design and installation as well as protection, monitoring, testing and continued compliance. TS131 is a dated technical standard: project teams should confirm the applicable current requirements with SA Power Networks and review the latest online document before relying on a printed copy.
Define the connection scope early
TS131 applies to systems capable of operating in parallel with the network, including systems designed not to export. It should be read alongside SA Power Networks’ connection requirements and Service and Installation Rules, and relevant Australian and New Zealand standards. The project proponent remains responsible for applicable approvals, licences and other obligations, including those associated with the Electricity Distribution Code and National Electricity Rules.
For inverter systems, the standard expects operation consistent with the principles of AS/NZS 4777. An inverter that does not comply with those principles must demonstrate compliance during commissioning and witnessing tests. The type and scale of generation, whether it exports, its connection voltage and its location all influence the protection and control arrangements required. Appendix connection examples in TS131 illustrate typical configurations, but do not replace assessment of a specific project.
Design protection around network conditions
Protection must detect credible faults and discriminate between faults within the generator’s installation and faults on the distribution network. Coordination with network protection matters because many feeders use automatic reclosing. If embedded generation remains connected after the network supply is lost, it can create equipment and safety risks, or interfere with restoration.
Anti-islanding and loss of communications
Anti-islanding protection must disconnect generation when the relevant part of the distribution network is de-energised. Its design needs to balance dependable island detection with the generating system’s required fault ride-through capability: protection should not trip unnecessarily during network faults where ride-through is required. Reconnection following restoration must observe the applicable return-to-service conditions.
For non-export systems, TS131 generally requires minimum-import protection unless an inter-trip scheme is installed. This protection monitors three-phase power at the connection point, or another agreed location, to ensure the site continues importing a minimum level of power. The standard describes a typical threshold of 10% of agreed maximum demand, with disconnection if import stays below that level for more than 0.4 seconds. The scheme must be fail-safe. A seamless-transfer proposal needs particular attention; where a temporary inhibit is agreed, reverse-power protection is also required.
Inter-trip protection may be required for exporting systems that do not follow AS/NZS 4777 principles, such as rotating generators, and in other cases determined by the network operator. Permissive signalling can control when a generator may operate in parallel. Where communications are required, loss of the link must result in disconnection under the standard’s specified arrangements. The site-side interface and trip path must also be designed to fail safe.
Coordinate protection functions
Depending on the system and connection, the protection design may include rate-of-change-of-frequency, under/over-frequency and under/over-voltage functions, as well as generator overcurrent, earth-fault and voltage-unbalance protection. Circuit-breaker-failure protection is required for specified larger or high-voltage connections. The standard also requires generation to disconnect if the DC or UPS supply to protection and control systems fails.
Protection settings must be developed for the proposed connection and coordinated with the network operator. TS131 includes particular settings for some inverter-connected systems, while other settings depend on the connection arrangement and network study. Teams should avoid treating example values as universal settings: submit proposed protection details for review and approval within the required project timeframe.
Plan for control, monitoring and commissioning
Protection is only one part of the interface. TS131 addresses reactive and real power control, quality of supply, fault level, fault ride-through, reclosing coordination and remote monitoring and control. Network monitoring or SCADA arrangements may be required so the operator can observe and manage generation on its network. The appropriate arrangement depends on project characteristics and the connection agreed with SA Power Networks.
Installation details also affect safe operation. For example, a switchboard containing network devices must have a manually operated main switch or isolator that isolates the complete board; it must not use motorised controls or connections to monitoring or measurement equipment. Where multiple inverter energy systems connect directly to one switchboard, the standard specifies a single inverter-supply main switch or isolator. A required network monitoring unit must be located somewhere safe and accessible.
Project teams should build review and testing milestones into the delivery plan. TS131 calls for protection details not already provided with the connection application to be submitted for review no less than three months before commissioning begins. Before connection, protection equipment must be tested and commissioned by a competent commissioning officer, with approved settings and test results recorded. The standard also covers pre-connection testing, compliance testing, post-connection commissioning, operating procedures and compliance monitoring and maintenance.
Make compliance part of ongoing operation
Connection approval is not the end of the engineering work. Settings and control schemes must remain aligned with approved arrangements, and changes should not be made without the required approval. Operating protocols between the generator and network operator help clarify how the installation responds to instructions and network conditions. Compliance monitoring and maintenance keep protection, communications and control functions dependable over time.
For engineers, integrators and plant decision-makers, the practical lesson is to treat an embedded generation connection as a coordinated network-interface project—not simply an equipment installation. Confirm the current standard and connection conditions early, establish the protection and communications philosophy, and schedule design review, commissioning evidence and ongoing maintenance before energisation. This approach helps align generation performance with the distribution network’s safety and operating requirements.