Product discontinuance planning is a practical part of keeping industrial control systems supportable over their operating lives. When a semiconductor supplier announces end-of-life for components used in controls, power circuits, or other equipment, engineering and operations teams need to identify exposure, evaluate replacement options, and make purchasing decisions before deadlines pass. ON Semiconductor’s July 2018 product discontinuance notice provides a useful example of the information teams should review.

The notice covered a range of devices and set out final-purchase and final-shipment dates, ordering conditions, and replacement information where available. Because these dates have passed, the document should be treated as a historical example—not as a current purchasing offer. Its details nevertheless show why a formal response to a component discontinuance matters.

What the 2018 notice specified

ON Semiconductor issued the notice on July 12, 2018, as part of a quarterly notification intended to consolidate product discontinuances. The company said affected products had declining sales and billings, or were associated with a manufacturing facility closure. Some devices could also be part of a portfolio renewal process.

For this notice, the stated last-time-buy date was July 12, 2019, and the last-ship date was July 12, 2020. The notice described a general window of 12 months from publication for placing final lifetime purchase orders and said products would not be delivered more than 24 months after the announcement. Acceptance was subject to reasonable order quantities, product availability, and applicable terms and conditions.

Orders for the discontinued products became NCNR: non-cancelable and non-returnable. The notice also said minimum order quantities or dollar amounts could be applied depending on available inventory. These conditions make it important to review not only a component’s final order date, but also the commercial terms and delivery schedule attached to a proposed buy.

Product discontinuance planning: a response for engineering teams

A discontinuance list is a starting point for a structured impact assessment. Compare every listed manufacturer part number with approved component records, bills of material, spare-parts lists, and active equipment designs. Confirm the exact part and suffix: similar device families or package variants should not be assumed to be interchangeable based on a partial number match.

Once a possible match is found, determine where the component is used and what equipment or assemblies depend on it. Engineering, procurement, and operations can then establish whether the change affects new production, maintenance spares, or both. The notice itself does not identify customers or applications, so each organization must make that connection using its own product and asset records.

Next, evaluate the supplier’s listed replacement rather than treating it as an automatic drop-in substitution. The 2018 notice names replacement part numbers, but does not provide electrical comparisons, qualification results, or application-specific approval. Engineers should therefore verify suitability against the relevant design requirements and internal change-control process before adopting a substitute.

For example, the notice lists LM224NG with LM224DR2G as a replacement, and LM358NG with LM358DR2G. It also identifies alternatives from Ricoh Electronic Devices for several listed ON Semiconductor products. These entries are useful leads for assessment; they are not, by themselves, evidence that a replacement has been validated for a particular circuit or operating environment.

When no replacement is listed

Not every affected device had a recommended replacement. The notice lists CAT93C56LI-G and CAT93C86LI-G with no replacement identified. For devices without a recommended alternative, ON Semiconductor stated that it had partnered with Rochester Electronics to carry remaining device inventory.

That option can inform a continuity review, but the notice does not guarantee a particular quantity or future availability. Teams should confirm current supply directly with the relevant supplier or sales channel and consider whether remaining inventory can cover the required equipment lifecycle. If it cannot, an engineering redesign may need to be assessed.

Manage deadlines, ownership, and supply terms

The notice asked customers who considered an affected product to be “Sole Source” to notify ON Semiconductor in writing within 90 days of receipt. It said the company and customer could negotiate an appropriate end-of-life arrangement. This highlights the value of reviewing supplier notifications promptly: any response period may be short, and sole-source status should be escalated rather than left solely to routine purchasing workflows.

A practical internal review can assign owners for the following tasks:

  • Engineering: verify part-number exposure, assess proposed replacements, and determine whether design changes or qualification work are needed.
  • Procurement: confirm availability, order quantities, NCNR terms, and shipment constraints before placing a final purchase.
  • Operations and maintenance: estimate the effect on production support and spare-parts planning using the organization’s own demand and asset data.
  • Supply-chain or product management: record deadlines, supplier communications, and the approved resolution for each affected part.

These actions help keep decisions traceable and connect component-level changes to equipment support requirements. They also reduce the risk of treating a suggested replacement or a last-time-buy opportunity as a complete technical solution.

Conclusion

The 2018 ON Semiconductor notice demonstrates the main elements of an effective response to component obsolescence: identify affected devices, understand the end-of-life timetable, validate any proposed replacement, and review purchase conditions before committing to inventory. For industrial automation teams, the practical lesson is to make discontinuance notices part of a coordinated engineering, procurement, and operations process. Early review gives decision-makers time to compare replacement, inventory, and redesign paths while keeping the limits of supplier-provided information clear.