A solar interconnection involves more than connecting a generation facility to the nearest transmission line. It also requires a review of system changes, land-use approvals and potential environmental effects. The AZ Solar 1 Interconnection Project near Salome, Arizona, provides a detailed example: a proposed photovoltaic (PV) facility would connect to an existing 115-kilovolt transmission line through a short tap, with associated work on transmission structures, substation relays and communications infrastructure.
How the AZ Solar 1 interconnection was structured
AZ Solar 1, LLC proposed a 32.5-megawatt PV facility on about 480 acres of private land. The developer could also add up to 27.5 megawatts of PV generation, 20 megawatts of battery storage, or both, depending on market considerations. The facility was to be operated so that its annual output would not exceed 50 average megawatts.
The proposed point of connection was the Little Harquahala to Harcuvar 115-kV transmission line, part of the Central Arizona Project. The U.S. Bureau of Reclamation built the line and holds the right-of-way on the relevant Bureau of Land Management (BLM)-managed land. The Western Area Power Administration (WAPA) operates and maintains it.
To connect the facility, WAPA proposed installing a tap on the existing line, consisting of up to two new pole structures and associated overhead conductors. Guy wires and buried anchors would be added to as many as three existing structures near the tap. A connection of less than 100 feet would link the transmission infrastructure to the solar facility’s switchyard, crossing BLM land. AZ Solar 1 would need a separate BLM right-of-way for the portion outside the existing transmission-line easement.
Transmission upgrades and operational coordination
The interconnection proposal included more than physical line work. WAPA also planned to upgrade relays in existing control buildings at the Harquahala and Harcuvar substations and install a microwave dish at its existing Pete Smith Peak microwave site. These items formed part of the transmission-related work considered alongside the proposed tap.
For engineers and project owners, the case highlights the range of interfaces that may need to be addressed when adding generation to an established network: structures and conductors at the connection point, protection equipment at substations, and coordination with the transmission asset owner. The environmental assessment describes the proposed work; it does not provide relay settings, protection schemes, communications protocols or a detailed engineering design. Those specifications should not be inferred from the project summary.
WAPA’s role was to evaluate and respond to the interconnection request under its responsibilities for transmission service. The interconnection agreement was intended to ensure that the requested connection would not degrade existing transmission reliability or service. Reclamation was to consider the proposed changes to its line and respond to requests for concurrence, while BLM was to respond to the right-of-way application for facilities on the land it manages.
Environmental review shaped the project decision
Because the proposal involved a federal agency decision, WAPA prepared an environmental assessment under the National Environmental Policy Act (NEPA). BLM’s Lake Havasu Field Office and Reclamation’s Phoenix Area Office participated as cooperating agencies. The assessment compared the proposed action with a no-action alternative, under which the interconnection and related development would not proceed as proposed.
The review considered air quality, biological and groundwater resources, historic and tribal resources, noise, public health and safety, land access, transportation, socioeconomic effects and visual resources. It also documented public scoping and consultation, including engagement with the Colorado River Indian Tribes. The assessment reported that WAPA found no effect on listed species because suitable habitat was not present in the project area, and that the State Historic Preservation Officer concurred with a finding of no historic properties affected.
Construction was expected to create temporary, localized emissions from equipment and vehicles, along with fugitive dust from disturbed soil. The assessment concluded that emissions would not cause an exceedance of National Ambient Air Quality Standards. It estimated total construction water use at about 200.18 acre-feet, primarily for the solar facility; projected operational use was about 20.62 acre-feet. The report characterized the facility’s groundwater effects as minor and WAPA’s construction water use as negligible.
Biological-resource analysis identified potential habitat disturbance and risks such as vehicle strikes during construction. Conservation measures were included to reduce the likelihood of direct harm to individual species. The project was also expected to create temporary noise effects, while operations would involve periodic maintenance and equipment noise. These findings show why environmental review matters to project planning: effects are assessed across construction, operation and decommissioning, not just at the electrical connection point.
What the finding of no significant impact means
In July 2019, WAPA issued a Finding of No Significant Impact (FONSI) based on the final environmental assessment. The agency determined that its proposed action—approving the interconnection request, entering into an agreement and implementing the described transmission upgrades—would not significantly affect the quality of the human environment under NEPA. Therefore, an environmental impact statement was not required.
A FONSI is an environmental-review determination, not a substitute for the technical studies, land approvals or agreements needed to carry out a project. In this case, the proposed work also depended on coordination among WAPA, Reclamation, BLM and the private developer. The solar facility’s construction and the associated land-use permissions were distinct from WAPA’s decision on the transmission interconnection.
Practical implications for project teams
The AZ Solar 1 case offers several planning considerations for renewable-generation developers, integrators and grid stakeholders:
- Define the connection scope clearly. Identify line taps, structure modifications, substation equipment changes and communications-related work as separate elements of the proposed interconnection.
- Map ownership and land authority early. Existing transmission rights-of-way do not necessarily cover every new connection segment; additional approvals may be required where facilities cross other managed land.
- Coordinate the environmental process with engineering and permitting. Construction footprints, access routes, water needs and conservation measures all inform the review of a proposed connection.
- Distinguish agency findings from project specifications. An environmental assessment explains the action and its anticipated effects, but it is not a detailed protection, controls or communications design package.
For industrial and energy-sector decision-makers, the central lesson is that solar interconnection planning spans electrical infrastructure, land rights and environmental compliance. A defined scope and early coordination among the transmission provider, land agencies and project developer help clarify the decisions required before a generation facility can connect to the grid.