Planning a 35MW solar power project involves more than selecting photovoltaic (PV) equipment and connecting it to the grid. Site conditions, land use, water requirements, community concerns and construction risks all influence how a project can be developed and operated. An Environmental and Social Impact Assessment (ESIA) prepared by Ghana’s Volta River Authority (VRA) for proposed sites at Kaleo and Lawra shows how these considerations can be brought into a utility-scale solar development plan.

The assessment covered a proposed expansion from an already permitted 12MW capacity to 35MW across four sites in the Upper West Region. Its approach combined project description, baseline environmental and social information, impact assessment, consultation and management planning. For engineers, system integrators and project owners, the case demonstrates why environmental controls and stakeholder requirements need to be considered alongside electrical design.

How the 35MW solar power project is structured

The proposed development is divided into two phases: 17MW in Phase 1 and 18MW in Phase 2. The sites comprise Kaleo Site 1, Kaleo Site 2, Kaleo Site 3 and Lawra, with a combined land area of 44.92 hectares. The project’s design uses ground-mounted, grid-connected PV panels on fixed-tilt systems. PV modules convert sunlight into direct current (DC), which inverters convert to alternating current (AC) for delivery to the electricity network.

The project plan also includes associated water-supply systems and a 34.5kV sub-transmission connection. Electricity from the generation units is to be combined, stepped up to 34.5kV and routed through switchgear and an overhead line to the network operated by Northern Electricity Distribution Company (NEDCo), a VRA subsidiary. This makes interconnection planning a core part of the development, not a separate task to address after the solar arrays are designed.

Why baseline conditions matter

An ESIA establishes the environmental and social conditions against which potential project effects can be assessed. The VRA assessment considered the physical environment, ecology and local socioeconomic context, drawing on data review, field visits and consultation. The study area included the immediate vicinity of the sites as well as a broader district context, recognizing that project effects may extend beyond the land occupied by the PV facilities.

The Kaleo and Lawra sites were described as degraded areas affected by farming, grazing and recurring bushfires. The assessment also documented vegetation and tree resources, nearby land uses and community features. These details help identify receptors that could be affected during construction or operation and inform decisions about avoidance, mitigation and monitoring.

For example, the assessment noted a historical burial site near Kaleo Site 1, nomadic settlements at or near Kaleo Site 2, and a shrine outside the Lawra project area. Such features can influence site preparation, access, construction sequencing and engagement with local stakeholders. Identifying them early gives project teams a basis for resolving concerns before they become construction constraints.

Managing environmental and community impacts

The assessment identified both potential benefits and adverse effects. Expected positive outcomes included employment opportunities, support for electricity stability, contribution to economic growth and reduced greenhouse gas emissions. Potential negative impacts included dust and vehicle emissions, soil or water pollution, flood risks, habitat loss, traffic hazards, worker or public injury, and loss of land or property.

Mitigation was organized around measures built into the project design, requirements to be included in contractor obligations, and additional actions for managing impacts. The EPC contractor was expected to provide health and safety, environmental protection and quality assurance plans. VRA was assigned a supervisory role during construction and responsibility for the operational phase.

Community engagement is another practical control, rather than simply a procedural step. The assessment highlighted priorities raised through consultation, including employment, compensation, changes in land use, public safety, community health, grievance resolution and continued engagement during construction and operation. A clear process for receiving and addressing grievances can help project teams identify concerns and assign responsibility for follow-up.

Water, operations and long-term planning

Water availability was identified as an important operational issue because PV modules require regular cleaning. The ESIA estimated wet-cleaning demand at between 19.5 and 84.5 cubic metres per year over a 20-year period. The assessment emphasized the need to ensure that project requirements do not adversely affect nearby communities’ drinking-water supply. This illustrates why water sourcing should be assessed in relation to local demand, not only the plant’s maintenance schedule.

The Environmental and Social Management Plan (ESMP) is intended to translate identified risks into implementation responsibilities. It covers mitigation, monitoring and reporting, training, schedules and cost estimates. For project managers, its value depends on linking those requirements to contractor work, site supervision and ongoing operational procedures.

Long-term planning also includes decommissioning. The report describes a typical project life expectancy of 20 to 25 years and states that equipment may be upgraded or the plant decommissioned. If decommissioning proceeds, project components are to be removed within 12 months, with the project owner responsible for meeting with the landowner before lease expiry and addressing removal and site restoration obligations.

Practical implications for solar project teams

The proposed Upper West Region development shows how a utility-scale PV project brings together electrical infrastructure, land management and environmental and social controls. Phased construction can shape design and installation planning, while grid connection, water supply and site-specific sensitivities require coordination across engineering, procurement, construction and operations teams.

For industrial and energy-sector decision-makers, the central lesson is to treat the ESIA and ESMP as working project tools. Integrating their findings into design decisions, contractor requirements, monitoring and community communication helps teams address risks throughout the project lifecycle—not only during permitting.