The Danfoss Turbocor compact inverter tester is designed to check switching functionality in the inverter modules used on TT and TG compressors. For maintenance teams, it offers a way to assess the inverter’s high-voltage section, IGBT paths and driver board without powering the compressor itself. Because the tester performs static checks only, results should be interpreted within that limited scope and the manufacturer’s stated procedure.
The work involves power electronics and potentially hazardous stored energy. Only qualified personnel who understand the equipment and its instructions should operate the tester. The compressor must be isolated, and the specified safety and setup steps must be followed before any test connections are made.
What the compact inverter tester checks
An inverter converts DC-link power into a controllable AC output. In Danfoss Turbocor compressors, insulated gate bipolar transistors (IGBTs) act as semiconductor switches, supporting precise control of the permanent-magnet motor’s speed and torque. The Bearing Motor and Compressor Controller (BMCC) manages that control in response to demand.
The compact inverter tester supplies the power needed to interface with the inverter during testing. Its capability is limited to static tests: it does not assess the compressor while operating. The procedure checks the inverter’s top and bottom sections, including IGBT voltage drop and the forward voltage drop of the free-wheeling diodes, as well as the driver board.
Inverter configurations vary across compressor models and revisions. The manual identifies SKiiP 292 and SKiiP 342 modules on major revision F and earlier TT300 compressors; SKiiP 613 on major revision G TT300 compressors; and SKiiP 513 or SKiiP 613 on TT350, TT400, TT500 and TT700 compressors. Confirm the applicable inverter arrangement before beginning.
Safety and preparation before testing
Do not perform this procedure with the compressor powered on. First isolate compressor power in accordance with applicable industry practices, then wait 20 minutes for the DC capacitors to dissipate their stored energy. The manual also calls for removing the compressor top covers, removing the soft start, and isolating the inverter by removing the snubber capacitors, DC-link capacitors and motor bus bars. Disconnect the inverter communication cable.
These steps are essential parts of the test setup, not optional conveniences. The tester is intended for use by personnel familiar with power electronics and thoroughly familiar with its operating instructions. Misuse can cause injury or equipment damage.
Setting up the tester and making measurements
With the inverter prepared, keep the tester’s supply selector off while connecting the supplied ribbon cable between the tester’s SKiiP GD connection and the inverter. Attach the SKiiP AC and DC test cables to the first inverter section, observing the identified alignment of the cable circuit boards. Connect the digital voltmeter (DVM) cable to an autoranging meter and match its positive and negative leads to the meter terminals.
The manual specifies several fixed setup positions: the SKiiP supply selector should be set to 24 V, the VCE/VF measurement selector to I supply, and switches 10 through 15 to the up position. Begin with the PWM signal generator off and the DVM set to DC voltage measurement. Connect the 24 V supply to the tester, then select the top inverter section.
To check the primary DC side, switch the supply selector to +24 V. Set the measurement selector to VCE (IGBT) to read the voltage drop-off state. The stated expected value is 170 VDC, with a minimum of 150 VDC. Record the reading before proceeding.
Interpreting IGBT and diode readings
For the IGBT forward voltage drop, hold the designated top-section test button and record the DVM value. The expected reading is 600–700 mVDC, with a stated tolerance of ±100 mVDC. Release the button and verify that the display returns to the voltage level recorded for the voltage drop-off state.
The manual emphasizes comparing all three phases: readings should be close to one another. If one or more phases are significantly higher or lower than the expected range, it states that the inverter should be replaced. This comparison matters alongside the nominal range; a single reading should not be considered in isolation.
To test the free-wheeling diode, select Vf (diode) and record the reading. The expected value is less than -600 mVDC. Return the measurement selector to off before changing the section selection. Repeat the procedure for the bottom section, using its corresponding test button, then switch the supply off and remove the test cables.
Repeat consistently across inverter sections
The inverter has three sections to test. After completing the first section, repeat the specified measurements for sections two and three, following the same sequence and recording top and bottom results separately. A results table should capture each section’s voltage drop-off state, IGBT forward voltage drop and free-wheeling diode reading. Consistent recording makes phase-to-phase comparisons easier and helps preserve a clear service record.
Before disconnecting or changing connections, return the relevant controls to their specified off positions. The tester procedure is a defined sequence; changing selector positions or connecting test leads without following it can undermine the test or create a safety risk.
Practical implications for maintenance teams
The compact inverter tester provides a focused diagnostic check of selected inverter functions on compatible Danfoss Turbocor TT and TG compressors. Its value lies in structured, repeatable static measurements—not in proving performance under operating conditions or replacing broader troubleshooting.
For technicians and maintenance leaders, the practical priorities are to confirm the inverter type, isolate and prepare the compressor correctly, follow the tester settings and connection sequence, and document readings for all three sections. Treat the specified voltage ranges and phase comparisons as part of the same assessment, and ensure that only qualified personnel perform the work. These practices keep the test aligned with its intended scope and support informed decisions about inverter condition.